Todo | Date |
Wiki started | S eptember 10, 2008 |
Overall robot design started | September 11, 2008 |
Mechanical design started | September 11, 2008 |
First Electrical prototype started | September 14, 2008 |
First Electrical prototype sent to AdvancedCircuits | October 31, 2009 |
Main Robot Order BOM1 out | November 17, 2008 |
Part List 1 | |
Quote from Don Wiggins (USC machine shop) approved | December 18, 2008 |
Start Mechanical Machining & Assembly | December 28, 2008 |
Cooling Block water proofing done | January 13, 2009 |
First Electrical prototype tested | January 21, 2009 |
Inner robot skeleton done | February 2, 2009 |
Robot body done | February 25, 2009 |
Electrical prototype 1.1 tested | February 26, 2009 |
Mechanical done | March 15, 2009 |
Robot Order BOM2 Sent out | April 15, 2009 |
Part List 2 | |
Final Electrical prototype Sent out | April 28, 2009 |
Final Mechanical modification sent to Machine shop | May 20, 2009 |
Final Electrical peripheral boards tested | May 31, 2009 |
Final Mechanical modification done | June 15, 2009 |
Robot Anodized | June 17, 2009 |
Power cable & Camera mount done | June 20, 2009 |
Final Electrical base boards tested | June 22, 2009 |
Robot Almost done | June 28, 2009 |
Robot done | July 7, 2009 |