| Todo | Date |
| Wiki started | S eptember 10, 2008 |
| Overall robot design started | September 11, 2008 |
| Mechanical design started | September 11, 2008 |
| First Electrical prototype started | September 14, 2008 |
| First Electrical prototype sent to AdvancedCircuits | October 31, 2009 |
| Main Robot Order BOM1 out | November 17, 2008 |
| Part List 1 | |
| Quote from Don Wiggins (USC machine shop) approved | December 18, 2008 |
| Start Mechanical Machining & Assembly | December 28, 2008 |
| Cooling Block water proofing done | January 13, 2009 |
| First Electrical prototype tested | January 21, 2009 |
| Inner robot skeleton done | February 2, 2009 |
| Robot body done | February 25, 2009 |
| Electrical prototype 1.1 tested | February 26, 2009 |
| Mechanical done | March 15, 2009 |
| Robot Order BOM2 Sent out | April 15, 2009 |
| Part List 2 | |
| Final Electrical prototype Sent out | April 28, 2009 |
| Final Mechanical modification sent to Machine shop | May 20, 2009 |
| Final Electrical peripheral boards tested | May 31, 2009 |
| Final Mechanical modification done | June 15, 2009 |
| Robot Anodized | June 17, 2009 |
| Power cable & Camera mount done | June 20, 2009 |
| Final Electrical base boards tested | June 22, 2009 |
| Robot Almost done | June 28, 2009 |
| Robot done | July 7, 2009 |